Will we ever see this in the new BPM. I am holding off moving from old workflow because this feature which used to exists no longer exists in the new BPM.

 

In the old workflow engine we had the ability to create a condition such as
When FIELD HAS NOT CHANGED FOR AT LEAST X DAYS?

 

When Quality Control Stage   Equals 'Quality Control Pending' for at least 2 days

OLD WORKFLOW

HOW TO DO IN THE NEW BPM? I'VE TRIED

WHEN ACCOUNT MODULE CHANGES WAIT 2 DAYS, AFTER 2 DAYS CHECK IF IT STILL = QC CONTROL PENDING IF SO THEN SEND OUT EMAIL.

Tried BPM

BUT THIS DOES NOT NECESSARY WORK ; BECAUSE THE FIELD MAY HAVE CHANGE WITHIN THE 2 DAYS FROM QC COMPLETED BACK TO QC PENDING.

 

I NEED TO CHECK THAT THE FIELD HAS NOT CHANGED FOR AT LEAST X DAYS?

 